Texas’ grid operator is developing a new process to evaluate multiple large-load interconnection requests at the same time. The question for cryptocurrency miners and data center developers that are ...
At the end of the batch study process, developers would have a set amount of time to make a financial commitment, Billo said, to demonstrate they will proceed with the project. After that, ERCOT could ...
Texas’ main electric grid operator is developing a new process to evaluate multiple large-load interconnection requests at the same time. The question for cryptocurrency miners and data center ...